Further to the recent weekend road closure we would thank you for your continued co-operation during this challenging Project, we would take this opportunity to inform you of a further one night closure to allow us to carry out operations which is outside the normal working day.
 
We have been in consultation with the Local Authority and Emergency Services to enable us to work over a single night which will allow us to install pre-cast concrete river culvert units.
 
The A465 will have to be closed to enable us to set up a 250 tonne crane to lift the units into place. The crane out riggers and the lorries delivering the pre-cast units will effectively block the whole width of the remaining A465 Heads of the Valleys.
 
The road closure will extend from Brynmawr Roundabout to Glanbaiden Roundabout, with the full Glanbaiden Roundabout fully open during the operation.
 
Station Road Gilwern and Station Road Clydach South will be able to cross the A465 as previously organised.

We currently envisage the work will be carried out between the times listed below:

20.00hrs to 06.00hrs - Monday 2nd November 2015
 
The work operation will include the use of the 250 tonne crane, vans, lorries, compressors and other small tools.
 
Emergency vehicles will be escorted through the works as on previous occasions.
 
Should you have any queries please contact our Public Liaison officer Phil Baker on his e-mail, phil.baker@costain.com or via the project contact number 0845 600 2664.
 