ulaaks
Member
Hi all!
I'm using this forum to log the progress of my dig!
1st June 2025:
Found the entrance to the cave. 1m of foliage had to be removed to reveal a rocky choked shaft.
2nd June 2025:
First attempt of a decent. Few rocks were removed but two large boulders made a decent unsafe. Thanks to Rowan (GUPA) for helping out.
24th June 2025:
Quick dig removing the two problematic boulders. Unfortunately half of the peat in the entrance collapsed in since last time so left the once clean very limestone covered in a meter thick layer of gunk. After removal, this allowed me to descend through the boulders to a choked floor about 2-3m down. Thanks to the Smoo crew for helping out.
6th August 2025:
My car broke down for a month so progress was halted. Once back most loose rocks were removed and a lot of peat that collapsed in was dealt with. A small 2m passage was observed underneath the choke that will require scaffolding and a lot of rock removal in order to be safely entered (not to mention both walls also need scaffolding). It also appears we're now in a large choked shaft that is gradually widening. The entrance has also (finally) been covered with a wooden pallet. Despite these setbacks things are looking promising. Thanks to Andrew (GUPA) and Ben (GUPA) for helping out.
I'm using this forum to log the progress of my dig!
1st June 2025:
Found the entrance to the cave. 1m of foliage had to be removed to reveal a rocky choked shaft.
2nd June 2025:
First attempt of a decent. Few rocks were removed but two large boulders made a decent unsafe. Thanks to Rowan (GUPA) for helping out.
24th June 2025:
Quick dig removing the two problematic boulders. Unfortunately half of the peat in the entrance collapsed in since last time so left the once clean very limestone covered in a meter thick layer of gunk. After removal, this allowed me to descend through the boulders to a choked floor about 2-3m down. Thanks to the Smoo crew for helping out.
6th August 2025:
My car broke down for a month so progress was halted. Once back most loose rocks were removed and a lot of peat that collapsed in was dealt with. A small 2m passage was observed underneath the choke that will require scaffolding and a lot of rock removal in order to be safely entered (not to mention both walls also need scaffolding). It also appears we're now in a large choked shaft that is gradually widening. The entrance has also (finally) been covered with a wooden pallet. Despite these setbacks things are looking promising. Thanks to Andrew (GUPA) and Ben (GUPA) for helping out.