Full weekend road closure: 23rd October - 26th October 2015
A full weekend road closure on the A465 Section 2 between Gilwern and Brynmawr is scheduled to commence at 20.00hrs on Friday 23rd October through until 06.00hrs on the Monday 26th October 2015.
The closure will facilitate a number of construction activities, but critically it is required to install a bat crossing underneath the carriageway and undertake rock blasting trials on some of the cutting slopes within the Clydach Gorge.
The recommended diversion from both ends of the closure can be seen here:
https://a465gilwern2brynmawr.files.wordpress.com/2013/05/ttro_15-full-closure-brynmawr-to-glanbaiden.pdf
During the course of the closures full access will be maintained through the site for emergency services vehicles which will be escorted by our traffic management team. Also we intend to maintain controlled access across the closure at the Saleyard and Gilwern junctions. An outline of the crossover arrangements can be seen here:
https://a465gilwern2brynmawr.files.wordpress.com/2013/05/ttro_15-full-closure-brynmawr-to-glanbaiden.pdf
A full weekend road closure on the A465 Section 2 between Gilwern and Brynmawr is scheduled to commence at 20.00hrs on Friday 23rd October through until 06.00hrs on the Monday 26th October 2015.
The closure will facilitate a number of construction activities, but critically it is required to install a bat crossing underneath the carriageway and undertake rock blasting trials on some of the cutting slopes within the Clydach Gorge.
The recommended diversion from both ends of the closure can be seen here:
https://a465gilwern2brynmawr.files.wordpress.com/2013/05/ttro_15-full-closure-brynmawr-to-glanbaiden.pdf
During the course of the closures full access will be maintained through the site for emergency services vehicles which will be escorted by our traffic management team. Also we intend to maintain controlled access across the closure at the Saleyard and Gilwern junctions. An outline of the crossover arrangements can be seen here:
https://a465gilwern2brynmawr.files.wordpress.com/2013/05/ttro_15-full-closure-brynmawr-to-glanbaiden.pdf