tim.rose2
Active member
Another good session in Hopeless yesterday. Richard arrived early equipped with a pile of wood and bucket of cement to look at stabilising some of the death boulders around the Steve's connection. Myself and Sas appeared at 10am and Gaynam joined us for the afternoon. When we arrived we found Richard led under one of the dubious bits of ceiling having removed all the previous supporting rocks on one side! Best part of 30 loads of spoil later we gave up at 4pm.
Richard spent a large part of the day constructing dry stone walls to support the ceiling and hold back some of the loose stuff in the area of the Steve's connection. More to be done but great progress. Sas & Gaynam assisted with spoil removal whilst I generated it.
The end of the cave is now an interesting place, however once again things have become unclear. As mentioned in the last report the ceiling of the tunnel we'd been following had become shattered. The right hand wall also appeared to take a right hand turn. We cleared some of the shattered ceiling heading up a couple of feet into the void. Initially this was about 8 to 12 inches high but is now substantially more having cleared a lot of rock. It seems like this void is a result of the roof of the phreatic tunnel parting company with the bedding layer 12 inches above and collapsing onto the mostly mud filled passage below. This means our dig is now effectively above the roof the hopeless tunnel. This is a similar situation to how we initially found the end of the cave back at the Steve's connection. It appears we have a passage heading off to the right and also something straight ahead. Digging down on the left hand side is what I believe to be the previously elusive left hand wall (currently buried under spoil awaiting to be taken out). Straight ahead on this level appears to be mostly rock peeling off in layers to create a void a few inches high. The course of action here will be to dig down and trace the route of the left hand wall probably having to remove both the peeling roof layer and a lot of mud. Digging down in the right hand passage appears to unearth a right hand wall heading off at 90 degrees to the main passage. So we now seem to have 2 digs! Ideally we need to completely empty this junction area to fully understand what's happening here, but only time will tell if we can be bothered. We cannot say for certain this is a junction rather than a right hand bend in the passage however the junction option feels more likely. The right hand passage looked like it's predominantly mud to dig. No sign of open passage yet. Hopeless is certainly hiding it's secrets well as we're now a good 5 to 10 m beyond the Steve's connection and it looks like a lot of hard work is required still.
Some photo's:
Richards timber store
Richards 'hopeless' wall
The spoil Sherpa's
The 'hopeless wall from the other side
The straight on dig (and our long poking pole). The left hand wall is 2ft below the pile of rocks on the left of the photo.
The right hand dig
Richard spent a large part of the day constructing dry stone walls to support the ceiling and hold back some of the loose stuff in the area of the Steve's connection. More to be done but great progress. Sas & Gaynam assisted with spoil removal whilst I generated it.
The end of the cave is now an interesting place, however once again things have become unclear. As mentioned in the last report the ceiling of the tunnel we'd been following had become shattered. The right hand wall also appeared to take a right hand turn. We cleared some of the shattered ceiling heading up a couple of feet into the void. Initially this was about 8 to 12 inches high but is now substantially more having cleared a lot of rock. It seems like this void is a result of the roof of the phreatic tunnel parting company with the bedding layer 12 inches above and collapsing onto the mostly mud filled passage below. This means our dig is now effectively above the roof the hopeless tunnel. This is a similar situation to how we initially found the end of the cave back at the Steve's connection. It appears we have a passage heading off to the right and also something straight ahead. Digging down on the left hand side is what I believe to be the previously elusive left hand wall (currently buried under spoil awaiting to be taken out). Straight ahead on this level appears to be mostly rock peeling off in layers to create a void a few inches high. The course of action here will be to dig down and trace the route of the left hand wall probably having to remove both the peeling roof layer and a lot of mud. Digging down in the right hand passage appears to unearth a right hand wall heading off at 90 degrees to the main passage. So we now seem to have 2 digs! Ideally we need to completely empty this junction area to fully understand what's happening here, but only time will tell if we can be bothered. We cannot say for certain this is a junction rather than a right hand bend in the passage however the junction option feels more likely. The right hand passage looked like it's predominantly mud to dig. No sign of open passage yet. Hopeless is certainly hiding it's secrets well as we're now a good 5 to 10 m beyond the Steve's connection and it looks like a lot of hard work is required still.
Some photo's:
Richards timber store

Richards 'hopeless' wall

The spoil Sherpa's

The 'hopeless wall from the other side

The straight on dig (and our long poking pole). The left hand wall is 2ft below the pile of rocks on the left of the photo.

The right hand dig
